Work starts on landslide solutions for Pacific Northwest Rail Corridor

EVERETT – Work is underway to help stabilize slopes and stop landslides along the Pacific Northwest’s only north-south passenger rail corridor.
Construction on a $16.1 million federally funded project began in early August. The project, which helps stabilize slopes above the rail line near Everett, represents the first step to help eliminate landslides and keep passenger rail service moving.

During long periods of heavy rain, rail line owner BNSF Railway temporarily suspends passenger rail service to ensure safety when a landslide occurs or a high-level threat of landslide exists. Alternate transportation is provided when rail service is suspended by landslides.

Between November 2012 and early January 2013, landslides cancelled a record number of daily trips. The Washington State Department of Transportation is working with government and private rail partners to review recent slope studies and historical slide data, with a goal of determining all factors contributing to landslides.

These projects are part of the $800 million federally funded high-speed-rail grants, awarded for 20 projects that will deliver more reliable, faster, more frequent Amtrak Cascades rail service. The grants are part of the 2009 American Recovery and Reinvestment Act high-speed-rail program administered by the Federal Railroad Administration.

In addition to the stabilization project near Everett, WSDOT starts construction on six additional federally funded rail projects in 2013.
 
Crews work to tame troublesome slide areas

MUKILTEO -- Work has begun on two projects intended to stabilize hillsides and keep winter mud from sliding onto the railroad tracks.

The state and BNSF Railway are reshaping the hillsides in two problem areas in Mukilteo where mudslides have smothered railroad tracks along the waterfront in recent years.

These projects are expected to be done by mid-October, ahead of the rainy season, said Gus Melonas, a spokesman for BNSF.

One of the hillsides is near the border of Mukilteo and Everett, Melonas said. The other is at the south end of Mukilteo near the Pacific Queen shipwreck.

Four more trouble spots in Everett and Mukilteo are targeted for fixes. These projects are still being designed and won't be done this winter, but all the work is scheduled to be done by early 2016, said Alice Fiman, a spokeswoman for the state Department of Transportation.

The department last year received $16 million from the federal government for mudslide prevention throughout the state.

The stretch between Everett and Seattle has been by far the most troublesome in recent years and all of that money will be funneled into the six targeted areas, state officials have said.
...
On Dec. 17 of last year, a slide knocked over several cars in a freight train as it moved below the bluffs southwest of downtown Everett, along Port of Everett property. No one was injured.

This spot will likely be the next one repaired and work could begin next spring, Melonas said.

Work at the Mukilteo-Everett border spot includes installing a steel-and-concrete retaining wall 10 feet high and 700 feet long, Melonas said. Debris has been cleared and ditches are being expanded, he said.

At the southern location, the hillside is being cleared of debris and loose soil and drain pipes could be installed there, Melonas said.

Other work in the future could include terracing of hillsides and installation of drain pipes, holding ponds and retaining walls, depending on the conditions at each location.

The railway has spent millions of dollars on its own projects along the corridor over the years, Melonas said, declining to provide a specific figure.

State geotech engineers are working with cities along the route to pinpoint areas where poor drainage control might be eroding slopes above the tracks, and to see what measures could be taken there, Fiman said.
 
Don't know how I missed this. Sorry. Here's IMO the most interesting and hopeful line in the Herald Net article:

State geotech engineers are working with cities along the route to pinpoint areas where poor drainage control might be eroding slopes above the tracks, and to see what measures could be taken there, Fiman said.

Sounds like maybe they're starting to deal with the problems at their source.
 