The Davy Crockett
Engineer
In addition to the detour over the Overland Route May 16 - 22 and June 1 - 7, 2012, Amtrak has posted the following:
April 16 - 23 and May 1 - 4, 2012
Westbound Train 5 Operates Later Denver - Emeryville
Westbound Train 5 will operate according to the normal published schedule from Chicago to Denver, arriving in Denver at 7:15 am. On April 16 through April 23 and May 1 through May 4, Train 5 will depart Denver at 11:05 am, three hours later than the times shown in Amtrak printed timetables, and will operate according to a later schedule at all remaining stations on the route through its arrival in Emeryville the following day. Additionally, passengers traveling west of Denver may encounter delays of up to one hour.
May 6, 7 and 8, 2012
Eastbound Train 6 Operates Later Grand Junction - Chicago
Eastbound Train 6 will operate according to the normal published schedules from Emeryville to Grand Junction. On May 6, 7 and 8, the train will depart Grand Junction at 1:23 pm, three hours later than the times shown in Amtrak printed timetables, and will operate according to an adjusted schedule at all remaining stations on the route through its arrival in Chicago the following day. Additionally, passengers may encounter approximately one hour delay west of Denver. On these three dates, passengers will not be able make connections in Chicago to trains departing before 7:00 pm or to Thruway motorcoach service to Galesburg.(Emphasis added)