    The contractor started work today on the new between the tracks platform. It will completely replace the south side only platform. It will include a tunnel under the tracks and realigning the tracks from Woodman Ave to about Sepulveda Bl. About 18 months to complete.
     
  2. Sep 11, 2017 #2

    WoodyinNYC

    W

    WoodyinNYC

    Conductor

    Joined:
    Aug 10, 2013
    Messages:
    1,515
    Location:
    NYC
    Is this station all Surfliner trains? Anyway, glad to see this work begin.
     
  3. Sep 11, 2017 #3

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    No. It is Surfliner, Metrolink, and Amtrak.
     
  4. Sep 11, 2017 #4

    Eric S

    E

    Eric S

    Conductor

    Joined:
    Dec 20, 2009
    Messages:
    2,459
    Location:
    Milwaukee
    In other words, Amtrak (Coast Starlight and Surfliners) and Metrolink
     
  5. Sep 12, 2017 #5

    rogers55

    rogers55

    rogers55

    Service Attendant

    Joined:
    Oct 26, 2007
    Messages:
    143
    Location:
    VNC
    I live close to the VNC station and always start my trips from there. The free parking is great too.
     
    Last edited by a moderator: Sep 12, 2017
  6. Sep 12, 2017 #6

    v v

    v

    v v

    Conductor AU Supporter

    Joined:
    Dec 5, 2012
    Messages:
    1,088
    Location:
    UK / France
    Does the VNC station continue to operate during the new platform construction?

    Thanks
     
  7. Sep 12, 2017 #7

    FrensicPic

    FrensicPic

    FrensicPic

    Conductor

    Joined:
    Jan 16, 2012
    Messages:
    2,830
    Location:
    LAX
  8. Sep 12, 2017 #8

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    Yes.
     
  9. Sep 12, 2017 #9

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    Amtrak operates the state owned Surfliners under contract to the state. They also operate Metrolink under contract to SCRRA (Southern California Railroad Association) who own these trains..
     
  10. Sep 12, 2017 #10

    WoodyinNYC

    W

    WoodyinNYC

    Conductor

    Joined:
    Aug 10, 2013
    Messages:
    1,515
    Location:
    NYC
    Interesting anyway, but I think this is not the same project. This link is to the northside platform, plans here from 2007, and I hope completed a few years back. Leemell's original post above says the new center platform will replace the existing southside platform. So, Phase I and now Phase 2?

    Anyway, a good location to doubletrack a stretch of mostly singletrack line. California has ambitions to muscle up the Surfliner service L.A.-Santa Barbara-San Luis Obispo. That will probably require many more such rebuilds to get the bottlenecks unclogged and the trains up to speed.

    The Amtrak LD bonus will be faster times for the Coast Starlight. Maybe it can arrive L.A. before 9 p.m., to give a better connection to the Sunset Ltd, which departs at 10 p.m. And even a connection to a Surfliner giving an earlier arrival in San Diego (now 1:06 a.m.) and adding that huge market to the Starlight's catchment.
     
  11. Sep 12, 2017 #11

    FrensicPic

    FrensicPic

    FrensicPic

    Conductor

    Joined:
    Jan 16, 2012
    Messages:
    2,830
    Location:
    LAX
    Yes, I see there is no between track platform in the proposal I linked to.

    The platform and Amtrak building is currently on the south side of Track 2. There is currently no north side platform - there is currently a short asphalt strip between Tracks One and Two which is sometimes used for boarding trains on track 1. That does not happen very often.

    As far as double tracking between CP Raymer and CP Bernson goes, the NIMBYS in Northridge have (thus far) been keeping that at bay! Double track already exists from Burbank Junction to CP Raymer in Van Nuys. The Chatsworth siding from CP Bernson to CP Topanga will become part of the double track. If that becomes reality then double track will exist from Burbank Junction all the way to CP Topanga in Chatsworth. Double track already exists from Burbank Junction to LA.
     
  12. Sep 12, 2017 #12

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    No, they changed the design to a center platform with a tunnel under tre tracks to access it. The first design was a platform addition to the north side. The double tracking from Raymer to Chatsworth is still awaiting a completed EIR. Metrolink offered a design that double tracked all but 1.5 miles, but the State Rail Bureau said no, it must be all of the tracks.
     
  13. Sep 13, 2017 #13

    FrensicPic

    FrensicPic

    FrensicPic

    Conductor

    Joined:
    Jan 16, 2012
    Messages:
    2,830
    Location:
    LAX
    OK...I see in March 2017 Board of Directors Meeting document (Item 7 on Page 24; related is Item 8 on Page 30 to reimburse UPRR for relocating tracks in Gemco Yard to accomodate).

    http://metrolink.granicus.com/DocumentViewer.php?file=metrolink_a0e5000649165814c347728d8114f6b6.pdf&view=1

    that Van Nuys would indeed be a center platform as you mention.

    Curious though, you opened this discussion stating that contractor had started work. I ride that line twice a day on my commute and, although Metrolink has been performing tie replacement between Burbank and Bernson for a few weeks now, I haven't seen any sign of track (either MT 1 or 2) realignment. I ask because why replace ties prior to beginning the re-alignment. Is this tie replacment activity what you see as the Van Nuys platform project beginning?

    Double track project - the "all but 1.5 miles" you mention...I'm guessing that is the track between Balboa Blvd and LIndley Avenue. Residential on both sides of the ROW.

    Not disagreeing, just wondering and clarifying! Regardless of how it takes place, it is definitely needed! Thanks.
     
    Last edited by a moderator: Sep 13, 2017
  14. Sep 13, 2017 #14

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    The contractor received "start work " order two weeks ago. Monday they blocked off the East end of the parking lot and began to establish a construction yard and offices. Yes on the double tracking.
     
  15. Sep 13, 2017 #15

    FrensicPic

    FrensicPic

    FrensicPic

    Conductor

    Joined:
    Jan 16, 2012
    Messages:
    2,830
    Location:
    LAX
    Thanks
     
  16. Sep 14, 2017 #16

    neroden

    n

    neroden

    Conductor

    Joined:
    Feb 23, 2014
    Messages:
    7,304
    Location:
    Ithaca, NY
    Weird though it may seem, I've frequently seen tie replacement done *before* track realignment, if the track was moving a fairly short distance. They first replace the ties. Then when it's realignment time, they remove the ballast and sort of pick up the entire ribbon of track, with ties, and slide it over to its new location. Apparently that's easier when the ties are in good condition.
     
  17. Sep 14, 2017 #17

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    Just a minor nit --- UPRR is doing the the maintenance --- it is their track.
     
  18. Sep 16, 2017 #18

    sechs

    s

    sechs

    Conductor

    Joined:
    Aug 19, 2005
    Messages:
    2,146
    Location:
    ATL
    Which track is UP?

    SCRRA owns the main to CP CO423 "Las Posas."
     
  19. Sep 16, 2017 #19

    FrensicPic

    FrensicPic

    FrensicPic

    Conductor

    Joined:
    Jan 16, 2012
    Messages:
    2,830
    Location:
    LAX
    That was my understanding, SCRRA.

    (Not "main line" but, Gemco Yard at Van Nuys belongs to UP.
     
    Last edited by a moderator: Sep 16, 2017
  20. Sep 16, 2017 #20

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    I believe all of the rest --- right at the station there are 4>3 tracks from the Gemco Yard, those I believe are UP's. It was certainly their crews I saw working on the ties there. Metro awarded a contract to them to move the tracks concurrent with construction contract.
     
    Last edited by a moderator: Sep 16, 2017
  21. Nov 17, 2017 #21

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    New pic and real construction has begun.
     
  22. Nov 23, 2017 #22

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    New pic and real construction has begun.

    VN Amtrak Station Const.jpg
     
  23. Sep 6, 2018 #23

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    Some new pics. The contractor has made major concrete pours and is beginning to tunnel under the tracks.

    vn5.jpg

    vn4.jpg

    vn3.jpg
     
  24. Jan 24, 2019 #24

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    The contractor has begun prep for the platform build and has done the rail moves.  Here are two videos of the rail work over last two years or so:  

     
  25. Sep 3, 2019 #25

    leemell

    leemell

    leemell

    Conductor

    Joined:
    Oct 5, 2009
    Messages:
    1,514
    Location:
    Los Angeles, CA
    The platform is really taking shape. About 90% of the concrete work is done. Last week they put up a canopy on the center platform. vny 1.jpg vny 2.jpg
     