From BL West:
https://www.brightlinewest.com/media/press-releases
January 16, 2024
LAS VEGAS – Brightline West is launching field investigation work in Nevada within the proposed rail corridor within Interstate 15 (I-15) right-of-way. The field work will advance final stages of design in...
Vandenberg SFB. The shuttle was supposed to launch from there on occasion, but never did. Never landed there. It is the primary launch site for polar orbiting satellites. It is in Lompoc between Santa Barbara and san Lan Luis Obispo right on the coast.
.
Brightline West posted this with the San Bernardino Board of Supervisors as to their current status with the Victorville to Rancho Cucomonga link. Very enlightening. Questions remain about Woodland Hills woman found alive after going missing in Zion National Park
Damage evaluated, repair designed and pre-construction is underway. Contractor is footing the entire cost. No schedule impact, not on critical path.
4
Like
About 40% of the Central Valley portion is complete. 77 miles of guideway complete. No track or system yet, RFP that went out about 4 months ago. Deadline was October. Track is near the end construction period.