Posted 13 January 2018 - 02:32 PM

On the contract status front, was there any discussion here of the Amtrak Inspector General report, date Nov 16 2017, which has useful information: TRAIN OPERATIONS: The Acela Express 2021 Program Faces Oversight Weaknesses and Schedule Risks

 

Anyone want to bet that all of these projects will be completed by 2021 or 2022?

Much delay and it will start to pinch. Deliver the cars on time and start to make money, to make the first payment in June. Otherwise, anyone spare some change?



#22 Acela150

Acela150

    Engineer

  • Members
  • PipPipPipPipPipPip
  • 7,141 posts
  • Gender:Male
  • Location:NS Harrisburg Division

Posted 13 January 2018 - 03:34 PM

 

 

 

...was there any discussion here of the Amtrak Inspector General report, date Nov 16 2017 ?  It stated there was already a 3 month slip or delay in the design and production schedule.

 

The infrastructure portion of the  program includes 10  projects on the Northeast Corridor totaling $850 million. ... four of these projects must be completed to run the new trainsets, and two must be completed to run trains on the higher-frequency timetable.

Anyone want to bet that all of these projects will be completed by 2021 or 2022?

Completed on schedule? Nah. Alstom says they're already 89 days behind. In the end, I'm betting that the Sunnyside Yard item entangled with the Metropolitan Transportation Authority is the one Least Likely To Succeed. YMMV

 

 

89 days isn't much on such a large order like this. I have faith in Alstom. Unlike the Bombardier-Alstom Consortium. 


These posts are my views and opinions.

Donate your spare time! Be a Volunteer Firefighter!
 
"Mainline 66W Recrew On Board at Abrams ready to head east when you can handle us, Ok 66W, ok on signal indication at Norris, take it to the Falls to wait for the window"

#23 DSS&A

DSS&A

    Lead Service Attendant

  • Members
  • PipPipPip
  • 172 posts

Posted Today, 08:01 PM

Alstom released a short YouTube video illustrating the progression of their HSR train set design. The link was kindly posted on railfan.net.


Edited by DSS&A, Today, 08:03 PM.